Tipping Drive Water Lines Phase 2

Pasadena, Newfoundland and Labrador

approvedDrinking WaterGIS
Federal contribution
$616,648
Federal share40%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 21, 2025
today
20232024202520262027
BuiltForecast

Approved 2.1 years before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Pasadena
Construction start
Apr 1, 2026(forecast)
Construction end
Dec 18, 2026(forecast)