Tipping Drive Water Lines Phase 2
Pasadena, Newfoundland and Labrador
Federal contribution
$616,648
Federal share40%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 21, 2025
today
20232024202520262027
BuiltForecast
Approved 2.1 years before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Pasadena
- Construction start
- Apr 1, 2026(forecast)
- Construction end
- Dec 18, 2026(forecast)