Forest Road Storm Sewer System

Pasadena, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$652,044
Federal share40%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
202220232024
Built
Program
Green Infrastructure Stream
Ultimate recipient
Town of Pasadena
Construction start
Apr 16, 2024(actual)
Construction end
Sep 26, 2024(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast May 4, 2024
  • Construction end2 months earlyforecast Nov 29, 2024