Water Treatment Improvements - Pasadena
Pasadena, Newfoundland and Labrador
Federal contribution
$689,194
Federal share40%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2019
202020212022202320242025
Built
Approved 4 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Pasadena
- Construction start
- Jan 3, 2022(actual)
- Construction end
- Nov 19, 2024(actual)
Against the original forecast
- Construction start3 months earlyforecast Apr 1, 2022
- Construction end12 months lateforecast Dec 2, 2023
Also in Pasadena