Back to projects

Trans-Canada Highway Pasadena to St. Judes

Pasadena, Newfoundland and Labrador

completeHighways and RoadsISF
Federal contribution
$616,743
Federal share31%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 11, 2009
2010
Built

Approved 2 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Aug 19, 2009(actual)
Construction end
Feb 22, 2010(actual)

Against the original forecast

  • Construction start5 weeks earlyforecast Sep 20, 2009
  • Construction end3 weeks lateforecast Jan 30, 2010