Arena and Pool

Mount Pearl, Newfoundland and Labrador

completeSportCC
Federal contribution
$4.0M
$4,014,159
Federal share30%

of $13.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 14, 2009
20102011
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Mount Pearl
Construction start
Jul 16, 2010(actual)
Construction end
Feb 2, 2011(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jun 1, 2010
  • Construction end21 months earlyforecast Nov 1, 2012

Also in Mount Pearl