Water, Sanitary/Storm Sewer, Asphalt, Curb, and Sidewalk Replacement – Spruce, Birch, Roosevelt Avenues; and Carroll Drive; and Watermain Lining Billard Avenue

Mount Pearl, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$2.4M
$2,376,018
Federal share40%

of $5.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 4, 2025
2023202420252026
Built

Approved 2.1 years before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of Mount Pearl
Construction start
Apr 24, 2023(actual)
Construction end
Jan 23, 2026(actual)

Against the original forecast

  • Construction start5 weeks earlyforecast Jun 1, 2023
  • Construction end3 months lateforecast Oct 31, 2025