Commonwealth Avenue Infrastructure Improvements

Mount Pearl, Newfoundland and Labrador

completeHighways and RoadsNRP
Federal contribution
$2.7M
$2,676,406
Federal share33%

of $8.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 11, 2017
201820192020
Built

Approved 2 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Ultimate recipient
City of Mount Pearl
Construction start
Oct 16, 2017(actual)
Construction end
Jun 3, 2020(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Aug 31, 2017
  • Construction end19 months lateforecast Oct 31, 2018