Water, Sanitary/Storm Sewer, Asphalt, Curb, and Sidewalk Replacement – Farrell Drive (from Holden Street to Evans Place)

Mount Pearl, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$2.5M
$2,461,310
Federal share40%

of $6.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 4, 2025
2023202420252026
Built

Approved 2.1 years before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of Mount Pearl
Construction start
Jun 1, 2023(actual)
Construction end
Feb 10, 2026(actual)

Against the original forecast

  • Construction end3 months lateforecast Oct 31, 2025