Street Improvements
Mount Pearl, Newfoundland and Labrador
Federal contribution
$2.2M
$2,230,071
Federal share33%
of $6.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 14, 2009
2010201220142016
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- City of Mount Pearl
- Construction start
- Jun 14, 2010(actual)
- Construction end
- Mar 15, 2017(actual)
Against the original forecast
- Construction start8 months lateforecast Oct 1, 2009
- Construction end11 months lateforecast Mar 31, 2016
Also in Mount Pearl
- Arena and Pool$4.0M
- Commonwealth Avenue Infrastructure Improvements$2.7M
- Water, Sanitary/Storm Sewer, Asphalt, Curb, and Sidewalk Replacement Farrell Drive (from Holden Street to Evans Place)$2.5M
- Water, Sanitary/Storm Sewer, Asphalt, Curb, and Sidewalk Replacement Spruce, Birch, Roosevelt Avenues; and Carroll Drive; and Watermain Lining Billard Avenue$2.4M
- Water, Sanitary and Storm Sewer, Asphalt, Curb and Sidewalk Replacement Jackman Drive$1.8M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26731 in the federal list. How to read these figures.