Water and Sewer Services-Deborah Lynn Heights
Paradise, Newfoundland and Labrador
Federal contribution
$717,217
Federal share33%
of $2.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 14, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Town of Paradise
- Construction start
- Jun 17, 2009(actual)
- Construction end
- Jan 26, 2010(actual)
Against the original forecast
- Construction start4 months earlyforecast Oct 15, 2009
Also in Paradise
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 26746 in the federal list. How to read these figures.