Topsail Road Widening
Paradise, Newfoundland and Labrador
Federal contribution
$1.2M
$1,161,574
Federal share29%
of $4.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 26, 2017
201720182019
Built
Approved 7 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Town of Paradise
- Construction start
- Jun 28, 2016(actual)
- Construction end
- Nov 7, 2019(actual)
Against the original forecast
- Construction start4 months earlyforecast Oct 31, 2016
- Construction end4 months lateforecast Jun 30, 2019