Sewage Treatment Plant Upgrading
Paradise, Newfoundland and Labrador
Federal contribution
$2.2M
$2,198,766
Federal share45%
of $4.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2016
2017201820192020
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Paradise
- Construction start
- Sep 25, 2017(actual)
- Construction end
- Mar 31, 2020(actual)
Against the original forecast
- Construction start2 months lateforecast Jul 26, 2017
- Construction end6 months lateforecast Oct 1, 2019
Also in Paradise