Schedule

Announced and approvedJul 6, 2016
2017201820192020
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Paradise
Construction start
Sep 25, 2017(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction start2 months lateforecast Jul 26, 2017
  • Construction end6 months lateforecast Oct 1, 2019