Back to projects

Kenmount Road Upgrading Phase 1

Paradise, Newfoundland and Labrador

underwayHighways and RoadsRNIS
Federal contribution
$1.1M
$1,083,725
Federal share33%

of $3.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2024
202420252026
BuiltForecast

Approved 8 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Town of Paradise
Construction start
Apr 14, 2025(actual)
Construction end
Jul 1, 2026(forecast)

Also in Paradise