Evergreen Village Upgrades - Phase 1

Paradise, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$1.1M
$1,129,989
Federal share40%

of $2.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 24, 2020
2021202220232024
Built

Approved 6 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Paradise
Construction start
Aug 15, 2022(actual)
Construction end
Jun 30, 2024(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 15, 2022
  • Construction end2 weeks earlyforecast Jul 15, 2024

Also in Paradise