Evergreen Village Upgrades - Phase 1
Paradise, Newfoundland and Labrador
Federal contribution
$1.1M
$1,129,989
Federal share40%
of $2.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 24, 2020
2021202220232024
Built
Approved 6 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Paradise
- Construction start
- Aug 15, 2022(actual)
- Construction end
- Jun 30, 2024(actual)
Against the original forecast
- Construction start2 months lateforecast Jun 15, 2022
- Construction end2 weeks earlyforecast Jul 15, 2024
Also in Paradise
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56798 in the federal list. How to read these figures.