Back to projects

Secondary Treatment at St. Thomas Line Wastewater Treatment Plant

Paradise, Newfoundland and Labrador

approvedDrinking WaterGIS
Federal contribution
$6.7M
$6,667,049
Federal share40%

of $16.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
today
20222024202620282030
BuiltForecast
Program
Green Infrastructure Stream
Ultimate recipient
Town of Paradise
Construction start
Jan 1, 2026(forecast)
Construction end
Dec 31, 2029(forecast)

Also in Paradise