Announced and approvedMay 14, 2009
2010201220142016
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Paradise
Construction start
Aug 20, 2010(actual)
Construction end
Mar 15, 2017(actual)

Against the original forecast

  • Construction start10 months lateforecast Oct 15, 2009
  • Construction end11 months lateforecast Mar 31, 2016