Highway 1 - Overpass Rehabilitation (eastbound lane) Southeast of the Medicine Hat Boundary
Federal contribution
$445,278
Federal share49%
of $906.4K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
2010
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Alberta
- Construction start
- Apr 4, 2010(actual)
- Construction end
- Jul 24, 2010(actual)
Against the original forecast
- Construction start2 months earlyforecast Jun 15, 2010
- Construction end8 months earlyforecast Mar 31, 2011