Resurfacing Work on Highway 524
Federal contribution
$3.0M
$2,977,848
Federal share50%
of $6.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Alberta
- Construction start
- Jun 21, 2010(actual)
- Construction end
- Dec 15, 2010(actual)
Against the original forecast
- Construction start7 weeks lateforecast May 1, 2010
- Construction end3 months earlyforecast Mar 31, 2011