Water Distribution Lines in Walsh
Federal contribution
$875,498
Federal share31%
of $2.8M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- County of Cypress
- Construction start
- May 6, 2010(actual)
- Construction end
- Oct 14, 2011(actual)
Against the original forecast
- Construction start5 weeks lateforecast Apr 1, 2010
- Construction end2 weeks earlyforecast Oct 31, 2011
Also in Cypress County
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 34580 in the federal list. How to read these figures.