Rehabilitation of the Westbound Lane of Highway 1
Federal contribution
$4.3M
$4,270,721
Federal share48%
of $8.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 29, 2010
2011
Built
Approved 2 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Alberta
- Construction start
- Aug 26, 2010(actual)
- Construction end
- Jun 13, 2011(actual)
Against the original forecast
- Construction start3 weeks lateforecast Aug 3, 2010
- Construction end4 months earlyforecast Oct 15, 2011