Back to projects

Highway 1 - Overpass Rehabilitation

Cypress County, Alberta

completeHighways and RoadsISF
Federal contribution
$453,212
Federal share50%

of $906.4K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
2010
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Alberta
Construction start
Apr 4, 2010(actual)
Construction end
Jul 24, 2010(actual)

Against the original forecast

  • Construction start2 months earlyforecast Jun 15, 2010
  • Construction end8 months earlyforecast Mar 31, 2011

Also in Cypress County