Grading of North Monarch Road
Federal contribution
$121,032
Federal share6%
of $2.2M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- County of Lethbridge
- Construction start
- Oct 18, 2010(actual)
- Construction end
- Jul 29, 2011(actual)
Against the original forecast
- Construction start5 weeks lateforecast Sep 13, 2010
- Construction end2 months earlyforecast Sep 30, 2011
Also in Lethbridge
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28750 in the federal list. How to read these figures.