Grading of North Monarch Road

Lethbridge, Alberta

completeHighways and RoadsISF
Federal contribution
$121,032
Federal share6%

of $2.2M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
County of Lethbridge
Construction start
Oct 18, 2010(actual)
Construction end
Jul 29, 2011(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Sep 13, 2010
  • Construction end2 months earlyforecast Sep 30, 2011

Also in Lethbridge

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28750 in the federal list. How to read these figures.