Turin Water Distribution System

Lethbridge, Alberta

completeDrinking WaterISF
Federal contribution
$699,461
Federal share33%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
County of Lethbridge
Construction start
Jun 28, 2010(actual)
Construction end
Aug 15, 2011(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Jun 14, 2010
  • Construction end3 months earlyforecast Oct 31, 2011