Enderby Intersection Improvements
Federal contribution
$1.8M
$1,750,000
Federal share50%
of $3.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedApr 7, 2009
ApprovedJan 25, 2010
201020112012
Built
Approved 10 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- Sep 27, 2010(actual)
- Construction end
- Dec 9, 2011(actual)
Against the original forecast
- Construction start3 weeks lateforecast Sep 7, 2010