Splatsin Community Building Improvements
Federal contribution
$1.5M
$1,476,497
Federal share100%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 15, 2021
20222023202420252026
BuiltForecast
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Splatsin Indian Band
- Construction start
- Sep 26, 2023(actual)
- Construction end
- Mar 31, 2026(forecast)
Against the original forecast
- Construction start6 months lateforecast Apr 4, 2023
Also in Enderby
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60527 in the federal list. How to read these figures.