Enderby Outdoor Pool
Federal contribution
$2.0M
$2,000,000
Federal share40%
of $5.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 11, 2022
20222023202420252026
BuiltForecast
Approved 2 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- City of Enderby
- Construction start
- May 12, 2025(actual)
- Construction end
- Jul 31, 2026(forecast)
Against the original forecast
- Construction start4 months lateforecast Jan 20, 2025