Highway 97A Resurfacing - East of Enderby to Springbend Road
Federal contribution
$583,591
Federal share50%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedAug 19, 2010
ApprovedSep 8, 2010
Built
Approved 3 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- Oct 12, 2010(actual)
- Construction end
- Nov 23, 2010(actual)
Against the original forecast
- Construction start2 months lateforecast Aug 1, 2010
- Construction end5 weeks earlyforecast Dec 31, 2010
Also in Enderby
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 41242 in the federal list. How to read these figures.