Back to projects

Wastewater Infrastructure Upgrades

Enderby, British Columbia

completeWastewaterISF
Federal contribution
$408,333
Federal share33%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2009
20102011
Built

Approved 3 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Enderby
Construction start
Sep 13, 2010(actual)
Construction end
Oct 17, 2011(actual)

Against the original forecast

  • Construction end2 weeks earlyforecast Oct 31, 2011

Also in Enderby

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36777 in the federal list. How to read these figures.