North Barriere Bridge Replacement

Barriere, British Columbia

completeHighways and RoadsISF
Federal contribution
$28,259
Federal share46%

of $60.9K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedApr 7, 2009
ApprovedJan 28, 2010
2010
Built

Approved 10 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Sep 8, 2009(actual)
Construction end
Oct 29, 2009(actual)

Against the original forecast

  • Construction end7 weeks earlyforecast Dec 20, 2009