Community Park Improvement

Barriere, British Columbia

completeRecreationISF
Federal contribution
$166,667
Federal share33%

of $500.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 13, 2009
ApprovedSep 1, 2009
20102011
Built

Approved 6 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
District of Barierre
Construction start
Oct 18, 2009(actual)
Construction end
Jun 24, 2011(actual)

Against the original forecast

  • Construction start5 months lateforecast Jun 1, 2009
  • Construction end3 weeks lateforecast May 31, 2011

Also in Barriere

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35459 in the federal list. How to read these figures.