Barriere Wastewater Treatment Upgrade
Federal contribution
$2.8M
$2,843,789
Federal share40%
of $7.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 22, 2024
today
202420252026
BuiltForecast
Approved 3 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- District of Barriere
- Construction start
- Feb 27, 2026(forecast)
- Construction end
- Oct 30, 2026(forecast)
Also in Barriere