Water Infrastructure Upgrades

Barriere, British Columbia

completeDrinking WaterISF
Federal contribution
$262,894
Federal share33%

of $788.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2009
20102011
Built

Approved 3 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
District of Barriere
Construction start
Jul 15, 2010(actual)
Construction end
Jul 1, 2011(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Jun 30, 2010
  • Construction end4 months earlyforecast Oct 31, 2011