Community Park Multi-Use Pathway

Barriere, British Columbia

completeActive TransportationISF
Federal contribution
$27,000
Federal share25%

of $108.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 13, 2009
ApprovedAug 10, 2009
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
District of Barriere
Construction start
Oct 5, 2009(actual)
Construction end
Oct 30, 2009(actual)

Against the original forecast

  • Construction start4 months lateforecast Jun 1, 2009
  • Construction end5 months earlyforecast Mar 31, 2010

Also in Barriere

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29573 in the federal list. How to read these figures.