Kiwanis Park Accessible Playground

Williams Lake, British Columbia

completeRecreationISF
Federal contribution
$70,000
Federal share25%

of $280.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 13, 2009
ApprovedAug 10, 2009
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Williams Lake
Construction start
Aug 4, 2009(actual)
Construction end
Oct 9, 2009(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jul 1, 2009
  • Construction end6 months earlyforecast Mar 31, 2010