Road Work on Maggie Lake Forest Service Road
Federal contribution
$148,500
Federal share50%
of $297.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedApr 7, 2009
ApprovedJan 28, 2010
2010
Built
Approved 10 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- Sep 15, 2009(actual)
- Construction end
- Oct 31, 2010(actual)
Against the original forecast
- Construction start5 months lateforecast Apr 30, 2009
- Construction end5 months earlyforecast Mar 31, 2011