Highway 4 - Kennedy Hill Safety Improvements

Ucluelet, British Columbia

completeHighways and RoadsNRP
Federal contribution
$13.5M
$13,500,000
Federal share25%

of $53.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 9, 2017
2017201920212023
Built

Approved 2 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
May 14, 2018(actual)
Construction end
May 31, 2023(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Apr 2, 2018