Back to projects

Ucluelet - Water Treatment System Upgrades

Ucluelet, British Columbia

underwayDrinking WaterGIS
Federal contribution
$3.8M
$3,840,000
Federal share40%

of $9.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 12, 2021
today
202220232024202520262027
BuiltForecast

Approved 3 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
District of Ucluelet
Construction start
Oct 28, 2025(actual)
Construction end
Nov 30, 2026(forecast)