Wastewater Treatment Lagoon Rehabilitation
Federal contribution
$869,045
Federal share50%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
2017201820192020
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- District of Ucluelet
- Construction start
- Jan 2, 2017(actual)
- Construction end
- Mar 11, 2020(actual)
Against the original forecast
- Construction end3 weeks earlyforecast Mar 31, 2020
Also in Ucluelet