Back to projects

Ucluelet - Amphitrite Point

Ucluelet, British Columbia

completeCultureCCRIS
Federal contribution
$544,320
Federal share40%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 3, 2020
2021202220232024
Built

Approved 2 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
District of Ucluelet
Construction start
Jun 1, 2023(actual)
Construction end
Oct 18, 2024(actual)

Against the original forecast

  • Construction start8 months lateforecast Oct 14, 2022