Watermain Replacement - Hastings
Federal contribution
$603,751
Federal share33%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipality of Trent Hills
- Construction start
- Jun 10, 2010(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction start6 weeks lateforecast May 1, 2010
- Construction end7 months earlyforecast Oct 31, 2011
Also in Trent Hills
- Construction of the Campbellford Recreation and Wellness Centre$4.1M
- Campbellford Potable Water Supply and Distribution System Upgrades$1.6M
- Replacement of the Hastings Treated Water Standpipe$1.0M
- Installation of Hastings Second Watermain Crossing of Trent River$827.2K
- Sewer Separation and Infrastructure Renewal$544.2K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30921 in the federal list. How to read these figures.