Construction of the Campbellford Recreation and Wellness Centre
Federal contribution
$4.1M
$4,134,669
Federal share26%
of $16.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 29, 2021
2022202320242025
Built
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Municipality of Trent Hills
- Construction start
- Apr 24, 2023(actual)
- Construction end
- Nov 25, 2024(actual)
Against the original forecast
- Construction end8 weeks lateforecast Sep 30, 2024
Also in Trent Hills
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57541 in the federal list. How to read these figures.