Campbellford Potable Water Supply and Distribution System Upgrades

Trent Hills, Ontario

completeDrinking WaterSCF
Federal contribution
$1.6M
$1,617,984
Federal share33%

of $4.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 2, 2015
2016201720182019
Built

Approved 2 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Municipality of Trent Hills
Construction start
Aug 1, 2017(actual)
Construction end
Mar 22, 2019(actual)

Against the original forecast

  • Construction end5 months lateforecast Nov 1, 2018