Replacement of the Hastings Treated Water Standpipe
Federal contribution
$1.0M
$1,043,700
Federal share40%
of $2.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 29, 2021
20212022202320242025
Built
Approved 5 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Municipality of Trent Hills
- Construction start
- May 6, 2024(actual)
- Construction end
- Jun 27, 2025(actual)
Against the original forecast
- Construction end6 months lateforecast Dec 15, 2024
Also in Trent Hills
- Construction of the Campbellford Recreation and Wellness Centre$4.1M
- Campbellford Potable Water Supply and Distribution System Upgrades$1.6M
- Installation of Hastings Second Watermain Crossing of Trent River$827.2K
- Watermain Replacement - Hastings$603.8K
- Sewer Separation and Infrastructure Renewal$544.2K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57275 in the federal list. How to read these figures.