Installation of Hastings Second Watermain Crossing of Trent River
Federal contribution
$827,227
Federal share40%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2022
2023
Built
Approved 3 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Municipality of Trent Hills
- Construction start
- Apr 24, 2023(actual)
- Construction end
- Aug 18, 2023(actual)
Also in Trent Hills
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62808 in the federal list. How to read these figures.