Garage Energy Savings Retrofit
Head, Clara and Maria, Ontario
Federal contribution
$12,648
Federal share33%
of $38.5K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Head, Clara and Maria, Township of
- Construction start
- May 3, 2010(actual)
- Construction end
- Aug 31, 2010(actual)
Against the original forecast
- Construction start5 months lateforecast Nov 20, 2009
- Construction end2 months lateforecast Jun 30, 2010
Also in Head, Clara and Maria
- District 11 - Project 1 - Near North Trails Association - Round Algonquin Park Tour Improvement$98.4K
- Head, Clara and Maria Municipal Building Repairs and Upgrades$80.0K
- Rehabilitation of Community Centre and Adjoining Library Facility$10.8K
- Admininistrative Building Lighting Upgrades$5.8K
- Administration Building Insulation Upgrades$3.3K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31223 in the federal list. How to read these figures.