Back to projects

Garage Energy Savings Retrofit

Head, Clara and Maria, Ontario

completeGreen EnergyISF
Federal contribution
$12,648
Federal share33%

of $38.5K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
May 3, 2010(actual)
Construction end
Aug 31, 2010(actual)

Against the original forecast

  • Construction start5 months lateforecast Nov 20, 2009
  • Construction end2 months lateforecast Jun 30, 2010

Also in Head, Clara and Maria