Back to projects

Administration Building Insulation Upgrades

Head, Clara and Maria, Ontario

completeAdministration, Emergency and Public WorksISF
Federal contribution
$3,272
Federal share26%

of $12.5K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Jan 18, 2010(actual)
Construction end
Apr 16, 2010(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Nov 20, 2009
  • Construction end11 months earlyforecast Mar 31, 2011

Also in Head, Clara and Maria