Admininistrative Building Lighting Upgrades

Head, Clara and Maria, Ontario

completeGreen EnergyISF
Federal contribution
$5,833
Federal share33%

of $17.5K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
May 3, 2010(actual)
Construction end
May 25, 2010(actual)

Against the original forecast

  • Construction start5 months lateforecast Nov 20, 2009
  • Construction end3 months earlyforecast Aug 31, 2010

Also in Head, Clara and Maria

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31327 in the federal list. How to read these figures.