Schedule

Announced and approvedJun 15, 2021
202220232024
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Feb 22, 2022(actual)
Construction end
Nov 27, 2023(actual)

Against the original forecast

  • Construction end4 weeks lateforecast Oct 31, 2023