Rehabilitation of Community Centre and Adjoining Library Facility
Head, Clara and Maria, Ontario
Federal contribution
$10,823
Federal share38%
of $28.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 4, 2021
20222023
Built
Approved 7 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Head, Clara And Maria, Township of
- Construction start
- Feb 22, 2022(actual)
- Construction end
- Oct 5, 2023(actual)
Against the original forecast
- Construction start5 weeks lateforecast Jan 18, 2022
- Construction end11 months lateforecast Oct 21, 2022
Also in Head, Clara and Maria
- District 11 - Project 1 - Near North Trails Association - Round Algonquin Park Tour Improvement$98.4K
- Head, Clara and Maria Municipal Building Repairs and Upgrades$80.0K
- Garage Energy Savings Retrofit$12.6K
- Admininistrative Building Lighting Upgrades$5.8K
- Administration Building Insulation Upgrades$3.3K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60779 in the federal list. How to read these figures.