Oakville Southwest (Phase 3) Wastewater Treatment Plant

Oakville, Ontario

completeWastewaterISF
Federal contribution
$16.7M
$16,733,333
Federal share33%

of $50.2M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Sep 7, 2009(actual)
Construction end
Aug 31, 2011(actual)

Against the original forecast

  • Construction start8 weeks earlyforecast Nov 1, 2009
  • Construction end2 months earlyforecast Oct 31, 2011